In April 2019, Stoos Bahnen received approval from the FOT to install a penstock on the old railroad trak to operate a Pelton turbine on the term that the installation is completed in the same year. The system was completely realized in 8 months from the beginning of cutting back the treetops on the old trak, which had been out of operation already for 4 years, up to the start up with a Premel control system at the end of December 2019. The pressure pipe has a length of 1.35 km and a pressure at the turbine of up to 80 bar. The turbine is designed for a max. energy output of 110 kW with one nozzle driving an asynchronous generator
Location
Switzerland
Sector
Renewable Energy
Technology
PAT and Pelton turbine
Company
Stoosbahnen
Completion
2019